Delayed Andheri-Ghatkopar metro will be delayed further

0
90

By Rajendra B Aklekar  www.dnaindia.com

The Andheri-Ghatkopar metro will be delayed further. Forget train operations, the MMRDA which said the line would be up and running by next year, is yet to clear land and hand over to the Mumbai metro engineers a portion of the plot which occupies a religious structure.

“A few structures of the mosque near Andheri station are coming in the way and holding up the steel bridge structure that is being pushed over the Western railway at Andheri station,” a site engineer told DNA.

“The MMRDA, which is required to hand over 100% right of way to us is yet to get the required permissions from the mosque authorities for demolishing the said structure. This has led to another delay and for two months, work of the steel bridge is seeing slow progress,” he said.

The engineer said the parapet wall and a small portion of a minaret is creating problems in the construction of the steel bridge which has already been delayed by over two years due to various problems of approvals, etc. The new delay will further advance the completion date of the long-awaited metro rail. More info

LEAVE A REPLY